Policymakers and grid operators warn that returning to the EU’s market could be crucial for realising the UK’s ambitious North Sea offshore wind plans, amid calls for regulatory reforms and closer regional cooperation.
The next phase of North Sea offshore wind deployment may be far harder to deliver unless the UK returns to the EU’s Internal Electricity Market, speakers at GOW 2026 said, as policymakers and grid operators face the challenge of turning a set of national power systems into something closer to a shared regional network.
Since Brexit, electricity trading across UK-EU interconnectors has operated under an explicit allocation model, requiring market participants to buy cross-border capacity separately before trading power on either side. At the event, Sally Lewis, head of policy and regulation at National Grid Interconnectors, said that scaling coordinated North Sea infrastructure would be very difficult under that arrangement. Julian Leslie, director of strategic energy planning and chief engineer at the National Energy System Operator, said returning to the IEM would make the process “a lot easier and more straightforward”, though he added that the current system has still supported trading, resilience and security of supply.
The discussion comes as the UK and EU negotiate possible UK participation in the bloc’s electricity market again. According to an explanatory memorandum published by the UK government, ministers have already sought authorisation to open talks on that question, underlining how far the issue has moved from abstract post-Brexit debate to live energy policy.
The stakes are significant. Nine North Sea countries are pursuing a plan to develop 100GW of cross-border offshore wind capacity by 2050, with turbines connected across multiple jurisdictions through interconnectors. That vision was reinforced in January, when UK and European leaders used the Hamburg North Sea summit to pledge closer cooperation on offshore wind, energy security and the resilience of critical infrastructure in the region.
For grid planners and developers, the central question is not only whether enough generation can be built, but whether the regulatory framework can keep pace. Lewis argued that multi-purpose interconnectors, which would link offshore wind assets directly to several countries, need a policy window this year if they are to secure approvals in time for deployment in the 2040s. Without changes to the rules, she said, those projects cannot proceed in a meaningful way.
Industry groups have argued that the prize is not merely technical efficiency but economic value. RenewableUK and National Grid have estimated that multi-purpose interconnectors could generate more than £13 billion in benefits for Great Britain and connected markets.
National Grid, meanwhile, is said to be hopeful that negotiations on power trading will be guided by energy security rather than wider political disputes. According to S&P Global Market Intelligence, the company believes the practical interdependence of the UK and European systems remains strong despite the more fragmented trading regime that followed Brexit. The European Council formally authorised the negotiations in March after exploratory discussions concluded in December 2025.
The broader policy direction is also becoming clearer. At the Hamburg summit in January, governments pledged to accelerate offshore wind development in shared waters and to strengthen cooperation on physical and cyber security for North Sea energy assets. For an industry seeking bankable routes to market, those commitments matter: they signal that the North Sea is being treated not just as a resource base, but as a strategic energy corridor that will require common rules as much as common cables.
Ofgem’s latest tender round for ownership and operation of major offshore transmission assets shows how quickly the UK’s offshore grid is expanding at home as well. The regulator is seeking bids for links associated with the 1.4GW Sofia wind farm in the North Sea, a reminder that the practical build-out of offshore infrastructure is already under way even before the deeper question of cross-border market reform is settled.
For now, the direction of travel is towards more integration, not less. The political agreements are in place, the technical ambition is sizeable, and the commercial case is strengthening. What remains unresolved is whether the market architecture will be simple enough to support the system the North Sea now demands.