Flintshire County Council has approved enfinium’s Parc Adfer carbon capture plant, a post-combustion unit on an energy-from-waste site in North Wales that would send captured CO2 to offshore storage through HyNet.
Flintshire County Council’s planning committee has approved full planning permission for Parc Adfer carbon capture, a project from energy recovery operator enfinium. The plant will sit beside the existing Parc Adfer energy recovery facility on Deeside Industrial Park in North Wales. It is a post-combustion capture unit. That means it removes CO2 from exhaust gas after the waste has burned. The permission covers the capture plant only, and the existing facility carries on operating.
The system will separate CO2 from the flue gas produced when the site treats unrecyclable waste. It then compresses the gas for pipeline transport. The CO2 will connect to the HyNet industrial decarbonisation cluster. From there it will go to depleted offshore gas fields beneath the Irish Sea for permanent geological storage. Capture at a waste plant differs from capture at a steel or cement site. The flue gas carries a mix of fossil and biogenic CO2, which shapes how developers and regulators count the climate benefit. The installation covers about 21,600 square feet next to the operating facility.
Local reports put the cost of the Parc Adfer carbon capture project at £200 million. Plans presented to the committee in October set out a capture volume of around 241,000 tonnes of CO2 a year, at a capture rate of up to 95%. Savills and LDA Design supported the application.
The committee had deferred its decision in October. Members wanted time to consult Natural England, Cheshire West and Chester Council and other regulatory bodies. About 50 public objections were received. They concerned carbon capture deployment and wider fossil fuel policy. The committee then backed the planning officer’s recommendation with one abstention. That near-unanimous vote clears the main planning hurdle for the Parc Adfer carbon capture scheme, which sits among the larger capture proposals in Wales.
Approval comes with conditions. A Section 106 legal agreement must be finalised, and the council delegated authority to complete it to its chief officer for place and growth. The agreement requires off-site biodiversity net gain schemes. It also sets a long-term monitoring, management and remediation framework that covers a minimum 30-year operational window.
Mike Maudsley, chief executive of enfinium, said: “We welcome Flintshire County Council’s decision to approve our plans to develop carbon capture at Parc Adfer.” He added that the decision advances progress towards delivering Wales’ largest carbon removal development. Backers of energy-from-waste capture call it removal because part of the CO2 in household waste comes from biogenic material such as food and paper. Storing that carbon underground takes it out of the atmosphere.
The Parc Adfer carbon capture scheme joins a wider group of UK projects that connect industrial and waste sites to carbon storage. The Cheshire-based Protos carbon capture project is one example. It has Veolia lined up to supply CO2 purification units.
Industry bodies have backed capture on energy-from-waste sites. Ben Burggraaf, chief executive of Net Zero Industry Wales, and Olivia Powis, chief executive of the Carbon Capture and Storage Association, both said that capturing CO2 from these facilities gives durable, high-integrity carbon removals. They also said it supports low-carbon power for manufacturing supply chains in North Wales.
Funding remains a variable for UK projects. The UK government signalled reduced carbon capture support at an industry conference in October. Final approval for the Parc Adfer carbon capture plant depends on the Section 106 agreement. Natural Resources Wales was also considering a separate environmental permit variation.
For industrial emitters in the HyNet region, the Flintshire decision adds one more planned source of CO2 for the shared transport and storage network. The next steps are the Section 106 signature and the environmental permit. Only after those can enfinium move the Parc Adfer carbon capture scheme towards construction. The reporting gives no construction date.