The Northern Endurance Partnership advances its project to build the UK’s first carbon dioxide transport and storage network, with offshore construction beginning at Hartlepool and significant regional economic impacts.
The Northern Endurance Partnership has moved into offshore construction on what is set to become the UK’s first carbon dioxide transport and storage network, with the latest work beginning at PD Ports’ Port of Hartlepool.
The scheme, being delivered with Saipem, is designed to move captured emissions from industrial sites across Teesside and the Humber to permanent storage beneath the southern North Sea. The first visible sign of the new phase came with the arrival of linepipe joints at Saipem’s logistics base in Hartlepool, where preparations are now under way for a 149-kilometre offshore pipeline and the associated landfall infrastructure.
According to PD Ports and NEP, more than 60% of the linepipe joints were manufactured locally at the former Liberty Steel pipe mill in Hartlepool, now operated by Corinth Pipeworks. The project has been presented as a significant boost for the regional industrial base, supporting around 150 skilled jobs and creating a further 35 roles, including apprenticeships.
NEP says the wider development, alongside Net Zero Teesside Power, is expected to underpin about 3,000 jobs. More than £2 billion of contracts have already been placed with over 260 UK companies, and the project is now around one-third complete, with onshore works already in progress.
The Port of Hartlepool will handle about 12,000 concrete-coated linepipe joints, with a combined weight of roughly 170,000 tonnes. PD Ports says between 40 and 60 people will be involved directly in the project across engineering, logistics, procurement and communications, while the port has invested more than £1 million in new pipe-handling equipment to support both this programme and future offshore cargo activity.
The scale of the scheme underlines the ambition behind the East Coast Cluster. Once operational, the network is expected to be capable of transporting and storing up to 23 million tonnes of carbon dioxide a year, which NEP says is roughly 20% of the UK’s annual emissions. That would make it one of the country’s most significant carbon capture and storage developments.
The offshore construction milestone follows a series of further project appointments. Earlier this year, SLB said it had won a contract to develop six carbon storage wells for NEP, while DNV has since been named independent certifier for the transport and storage system, responsible for verifying compliance with the project’s licence requirements.