Polskie Elektrownie Jądrowe has signed an amendment enabling detailed design work and site preparations for Poland’s first commercial nuclear power station, keeping the project on track for operation in the late 2030s amidst ongoing negotiations for the final EPC contract.
Polskie Elektrownie Jądrowe (PEJ) has signed an amendment to its Engineering Development Agreement (EDA) with the Westinghouse‑Bechtel consortium that will allow the next stage of preparatory work for Poland’s first commercial nuclear power station to proceed while negotiations over the final engineering, procurement and construction (EPC) contract continue, the trade publication NucNet reported.
According to the NucNet report, the amendment enables detailed design work for the nuclear island, turbine island and balance of plant, and clears the way for expanded geotechnical campaigns. PEJ said the next phase of surveys is scheduled for 2026 and will include about 1,000 boreholes totalling some 15 km of drilling and roughly 7,000 laboratory tests. Earthworks to level the site and build temporary internal roads are due to start in the first half of the year, and procurement of long‑lead items will continue, the company added.
PEJ president Marek Woszczyk was quoted as saying: “In terms of the current negotiations, we want to proceed reasonably quickly, which is why the amendment signed today allows us to continue talks on the EPC contract, focusing on quality, with no negative impact on the project”. The company said some work originally intended for the EPC has been brought forward into the amended EDA to protect the project schedule.
The project envisages three Westinghouse AP1000 reactor units at the Lubiatowo‑Kopalino site in Pomeranian Voivodeship on the Baltic coast. The original EDA was signed on 28 April 2025 at a ceremony attended by the US energy secretary and Polish prime minister, according to a statement from the US Department of Energy, which described the initiative as part of a wider US‑Poland civil nuclear cooperation effort. Bechtel and Westinghouse have issued parallel statements outlining the EDA’s role in advancing site development, regulatory documentation and geological studies ahead of an EPC agreement targeted for the end of 2025.
Financial backing for the scheme has shown strong early interest. PEJ said it has received 26 preliminary bank offers to support debt financing, with total indicative support several times larger than the required debt. The European Commission on 9 December approved public aid estimated at PLN 60 billion, a measure PEJ and government officials say unlocks broader financing. The company has described total capital expenditure for the programme at around €42 billion in nominal terms, with debt planned to cover about 70% of the cost and the remainder to come from the state budget.
The European Commission’s statement indicated the plant is scheduled to begin operation in the second half of the 2030s. Poland’s energy minister Milosz Motyka told a press conference: “We can now freely begin the next investment steps.” Industry participants and governments involved portray the amendment as a pragmatic step to maintain momentum while technical and commercial terms for the EPC are finalised.
Observers note the amendment preserves schedule flexibility but does not remove remaining commercial and regulatory milestones. The EPC contract will ultimately define risk allocation, detailed costs and delivery timelines, and its finalisation will be critical to converting preparatory works into full construction. According to Bechtel, the EDA remains effective until execution of the EPC agreement, which the consortium and PEJ have been targeting by the end of 2025.
As Poland moves to diversify its power mix and decarbonise industry, the project is being framed by government and consortium statements as a strategic, long‑term investment in energy security. The company claims the staged approach embodied in the amended EDA balances timely progress on site preparations with continued negotiation of the contractual framework that will govern the multi‑billion‑euro build.