GASCADE has completed a pioneering 400-kilometre conversion of high-pressure natural gas pipelines for hydrogen transport in Germany, paving the way for large-volume industrial hydrogen supply and cross-border integration by 2029.
GASCADE has brought into service a roughly 400-kilometre central section of Germany’s planned hydrogen core network by converting existing high-pressure natural gas pipelines for hydrogen transport, the company said, a move aimed at giving industry access to large-volume hydrogen corridors and supporting decarbonisation of hard-to-abate industrial processes.
The pipeline axis runs north–south from the Baltic Sea region to Saxony-Anhalt and is part of the operator’s “Flow – making hydrogen happen” programme. According to GASCADE, the conversion uses existing pipework with a diameter of 1.4 metres and was completed in mid-December 2025; the company says the infrastructure is now available to the market. GASCADE operates a wider high-pressure network of about 3,700 kilometres and intends to progressively convert sections for hydrogen transport.
“With the successful conversion of 400 kilometres of pipeline, we reliably provide large-volume and central hydrogen infrastructure,” GASCADE Managing Director Ulrich Benterbusch said in the company announcement, describing the work as a technical pioneering achievement. GASCADE Managing Director Christoph von dem Bussche added: “Flow – making hydrogen happen is more than a technical project. It is a promise for the future,” emphasising the scheme’s European dimension and planned cross-border linkages.
The newly operational section is intended to improve planning security for industrial customers by providing a backbone for feedstock and energy supply as companies shift from fossil feedstocks and on-site fuels to low‑carbon hydrogen. GASCADE says the axis can receive hydrogen from multiple sources including supplies from the European Baltic Sea region, imports via the port of Rostock and production on the Baltic coast, notably at Lubmin.
Industry observers and project partners point to concrete near-term supply routes. According to a GASCADE press release, HH2E’s green hydrogen production site in Lubmin has been confirmed as connected to the EUGAL pipeline lines, with HH2E planning to start production by the end of 2025 and the option to blend green hydrogen into the existing network. Such local production and import options are positioned by GASCADE as complementary to future cross-border flows.
GASCADE frames this operational milestone as the first step toward further southern connections planned for completion by 2029. The company has said pipeline links to Poland, the Czech Republic, Bavaria and Austria are part of the roadmap, to be achieved partly through further conversions of existing infrastructure and partly through new construction. That sequencing aims to stitch northern import routes and coastal production into industrial centres in southern Germany.
Technical and safety measures used during conversion were outlined by the operator: the project included controlled discharge and burning-off of residual natural gas to prepare pipelines for hydrogen service. GASCADE dates the conversion activity to 2025 and characterises the programme as establishing one of the first large-volume north–south hydrogen axes in Germany.
While GASCADE presents the conversion as creating immediate market access for hydrogen, the full utility of the corridor will depend on timely ramp-up of low‑carbon hydrogen production, import volumes arriving at Baltic ports, and the completion of planned southern and cross-border connections. For industrial decarbonisation planners, the new axis offers a materially stronger basis for off‑site hydrogen procurement, but the scale and timing of available volumes remain contingent on allied projects and offtake arrangements.