The Northern Endurance Partnership secures a seabed lease from The Crown Estate, paving the way for the UK’s first large-scale offshore CO2 storage project, with operations anticipated to start in 2028.
The Northern Endurance Partnership (NEP) has moved from planning to delivery after signing a commercial seabed lease with The Crown Estate that clears the way for the United Kingdom’s first large-scale offshore carbon capture and storage (CCS) project to enter construction.
According to Carbon Herald, the agreement secures NEP’s route for an offshore pipeline and the Endurance storage complex, a deep saline aquifer in the southern North Sea with combined capacity across nearby formations estimated at around 1 billion tonnes of CO2. The Crown Estate lease is framed as the nation’s inaugural commercial instrument for permanent offshore CO2 storage and the associated pipeline corridor, creating a precedent for subsequent projects around the UK coastline.
The move follows a sequence of regulatory and commercial milestones achieved late in 2024 and early 2025. NEP reached financial close on the first tranche of onshore CO2 transport infrastructure for Teesside and concluded financing for the offshore export pipeline, while obtaining the UK’s first offshore carbon storage permit from the North Sea Transition Authority, industry sources report. Construction work is already mobilising and the partnership remains on course to begin operations in 2028, with injection activities scheduled to continue into the mid-2050s.
NEP is an incorporated joint venture led by bp, Equinor and TotalEnergies. TotalEnergies holds a reported 10% stake and the partnership has indicated an initial storage throughput target of up to 4 million tonnes of CO2 per year, intended to serve early capture projects including Net Zero Teesside Power and future industrial abatement schemes across the East Coast Cluster. Industry commentators and project partners have characterised Endurance as critical infrastructure to decarbonise energy-intensive sectors such as power generation, chemicals and heavy industry while supporting regional employment and supply-chain activity in north‑east England.
Key delivery contractors have been announced as the scheme transitions to execution. According to corporate releases, Xodus provided technical advisory support to achieve financial close and confirmed plans for a roughly 145 km offshore pipeline and subsea injection works, with installation activity expected to commence in mid-2025. SLB has been appointed to deliver carbon storage site development services, including the construction of six injection wells under its Sequestri™ portfolio, while Halliburton will supply completions and downhole monitoring hardware, largely manufactured at its Arbroath facility.
The partnership’s proponents argue the project will function as a backbone for a broader UK carbon management network, unlocking cumulative investment in transport and storage that could accelerate deployment of capture projects nationally. According to TotalEnergies’ statement, the infrastructure includes an onshore gathering network, compression facilities and subsea injection systems located around 1,000 metres beneath the seabed.
For developers, industrial offtakers and supply‑chain firms focused on decarbonisation, Endurance presents a tangible example of project sequencing: securing seabed rights and regulatory permits, achieving financial close, appointing specialist service providers and moving quickly into fabrication and drilling. The lease with The Crown Estate also establishes a commercial template that could reduce transactional uncertainty for future UK storage licences.
Risks remain. Deliverability will depend on timely execution of offshore construction, well drilling and commissioning, as well as sustained demand from capture projects to fill the initial 4 Mtpa capacity and to justify further expansion of storage operations into the mid-21st century. Market signals for long‑term offtake, clear regulatory oversight and continued government support for cluster development will be pivotal to realising the broader ambitions NEP’s backers articulate.
As the UK seeks to scale industrial decarbonisation, the Endurance project will be watched as a test case for whether ambitious storage capacity, aggregated transport infrastructure and private–public co‑investment can be translated into operational CO2 removal at scale.