India aims to develop 100 GW of pumped hydro storage by 2036 as part of its push towards a renewable-dominated energy system, according to a government roadmap unveiled at a recent power policy shivir.
The Ministry of Power’s two-day Chintan Shivir, held on 22–23 January 2026 in Parwanoo, brought senior officials, regulators, industry executives and academics together to set policy priorities for India’s electricity transition and to map out large-scale investment in long-duration storage.
According to the Central Electricity Authority report released at the meeting, India aims to develop 100 GW of pumped hydro storage (PHS) by 2035–36 as a backbone for a renewable-dominated system. The roadmap frames PHS as a durable, low-carbon and largely domestically supplyable solution capable of providing large-scale energy shifting, frequency support and black-start services as variable renewable generation grows. The CEA projects national storage needs rising from about 62 GW by 2029–30 to 161 GW by 2034–35, with further escalation to several hundred gigawatts later in the 2040s as solar and wind penetration deepens. The report assesses existing projects, state-level potential and a phased rollout that prioritises off-river closed-loop schemes to limit environmental and rehabilitation impacts and to shorten project gestation.
The authority estimates total PHS potential at roughly 266.85 GW, of which about 209 GW derives from off-river closed-loop sites. As of 31 December 2025, operating pumped storage stood at about 7.18 GW, with roughly 11.62 GW under construction and a further tranche, more than 9.5 GW, having received CEA concurrence but not yet progressed to construction. Projects in survey, investigation or DPR preparation account for an additional roughly 74.9 GW of identified capacity. Under the plan, India would need an average annual addition of about 9 GW of pumped storage to meet the 100 GW objective; the CEA places the indicative capital requirement for that build-out at about ₹5.8 lakh crore, estimating a per‑megawatt cost in the region of ₹6 crore. The authority notes that closed-loop off-stream projects can have shorter lead times, around four years, potentially enabling faster commissioning in the latter half of the decade.
The Shivir’s agenda extended beyond storage. Ministers and officials discussed the Draft Electricity Amendment Bill, 2026 and the Draft Electricity Policy 2026, which set ambitious usage and emissions intensity milestones, including per capita consumption targets and a 45% reduction in emissions intensity by 2030, within a long‑range trajectory to net zero. Participants also debated measures to accelerate nuclear capacity, optimise transmission and distributed resources, and to embed storage, both grid-scale and behind-the-meter, into planning and markets.
A central focus was repair and reform of distribution utilities. Presentations at the event examined operational, financial and regulatory steps to restore DISCOM viability: rationalising cross-subsidies, enhancing industrial competitiveness, streamlining tariff processes and reducing avoidable disputes over connectivity and change‑in‑law claims. Officials emphasised standardisation, digitisation and clearer procedures as tools to cut litigation, lower costs and improve the investment climate for both public and private players.
The Chintan Shivir also published the 14th Integrated Rating and Ranking of Power Distribution Utilities, which evaluated 65 DISCOMs. Thirty-one utilities secured A+ or A grades; Torrent Power Ahmedabad and Torrent Power Surat led the overall rankings for FY2024–25, while among state-owned entities Uttar Gujarat Vij Company Limited recorded the top performance. The ratings are being positioned as a lever for incentivising timely reform and operational improvements.
Industry and policy players at the meeting were urged to co‑ordinate closely across central and state governments, regulators and utilities to deliver the storage pipeline and distribution reforms on schedule. Achieving the scale of pumped storage envisaged will require sustained capital mobilisation, faster permitting and construction cycles for off‑stream projects, and regulatory frameworks that align revenue models with long‑duration storage services. For industrial decarbonisation stakeholders, the CEA’s roadmap signals both large investment opportunities in long‑duration flexibility and the need for integrated planning across generation, transmission, storage and demand‑side actors to secure a resilient, low‑carbon grid.