ArcelorMittal plans a USD900 million investment in India, developing hybrid renewable clusters in Maharashtra, Rajasthan, and Gujarat to double its renewables capacity and support steel decarbonisation efforts.
ArcelorMittal has announced a USD900 million investment to develop three renewable energy projects in India that together will add about 1 GW of capacity to its portfolio, the company said in a statement. According to the report by Powerline, the assets will be located in Maharashtra, Rajasthan and Gujarat and the electricity will be supplied to AMNS India, the joint venture between ArcelorMittal and Nippon Steel.
The proposed portfolio comprises a 36 MW solar plant in Amaravati, Maharashtra; a 400 MW solar installation in Bikaner, Rajasthan paired with a 500 MWh battery energy storage system (BESS); and an integrated renewable cluster in Bachau, Gujarat combining 250 MW of wind, 300 MW of solar and battery storage. ArcelorMittal’s corporate release states the capital expenditure for the three projects is expected to total about $0.9 billion and that the build will double its renewables capacity in India to around 2 GW and lift its global renewables capacity to roughly 3.3 GW.
Timelines reported by Financial Express and other trade outlets indicate phased commissioning, with the Amaravati solar plant targeted for delivery in the first half of 2027 and the larger Bikaner and Bachau complexes scheduled for completion by the first half of 2028. Industry reporting also describes the Bachau site as a hybrid “cluster”, reflecting a trend among industrial offtakers to pair wind, solar and storage within a single integrated project to improve firming and grid services.
The projects will feed power directly into AMNS India’s operations, supporting the steelmaker’s decarbonisation objectives. Financial Express and Business Today note the investment is framed as reducing the carbon intensity of AMNS India’s supply, while previous arrangements , such as a separate partnership between ArcelorMittal and Greenko to develop renewable capacity and storage in Andhra Pradesh , show the company is pursuing multiple routes to secure long‑term, low‑carbon supply for its Indian steel operations.
Analysts and developers cite several commercial drivers for the move: stabilising long‑term power costs for energy‑intensive steel production, meeting corporate and investor ESG expectations, and hedging against the volatility of grid emissions factors. Industry data shows that pairing large‑scale renewables with multi‑hour storage is becoming standard for heavy industrial offtakers seeking higher renewable penetration without relying solely on merchant markets.
ArcelorMittal describes the announcement as part of a broader strategy to expand captive and long‑term contracted renewables. The company said in its release the new projects will be dedicated to AMNS India, although project structuring, procurement partners and offtake contracting details were not disclosed in full in the initial public statements. Journalistic reporting indicates the projects will be developed under a mix of direct ownership and third‑party partnerships, mirroring recent sector practice where developers combine balance‑sheet investment with specialist renewable operators to manage construction and operational risk.
For industrial decarbonisation professionals, the package underscores two practical trends: growing use of hybrid renewable clusters to deliver more predictable renewable energy to heavy industry, and the scale of capital being committed by global steelmakers to secure long‑term green power. How these projects are financed, the allocation of grid connection and curtailment risk, and the precise contract structures with AMNS India will determine the projects’ effectiveness in reducing Scope 2 emissions and the lessons they offer other energy‑intensive sectors.